APEC Leaders' Week takes place on Phu Quoc in November 2027. What is being built, how far along it is, where the numbers disagree and what it means for tourists.

If you visited Phu Quoc a few years ago, you will barely recognise the island. Where empty beaches and dirt roads used to stretch, the steel frame of a huge convention centre is now rising, a wide boulevard is being laid out and a second passenger terminal is growing at the airport. The reason is one: in November 2027 Phu Quoc hosts APEC Leaders’ Week, the forum of Asia-Pacific economies. For the island it is the construction project of a lifetime; for tourists the question is what will change and whether to go that year.

We have gathered data from Vietnamese and international press for 2025-2026, noted where the figures diverge and picked out what matters to a traveller. All information is current as of 24 November 2026.

In short. APEC 2027 on Phu Quoc:

  • When: APEC Leaders’ Week is scheduled for November 2027; exact dates have not been named.
  • Where: the Phu Quoc special zone, An Giang province.
  • Deadline: all 21 key projects must be substantially completed and tested by 31 May 2027.
  • Airport: a new T2 terminal, a VIP terminal and a second runway; the first phase is stated to start operating in April 2027.
  • For tourists: the sources name no restrictions, closures or price rises; local authorities say normal traffic will continue.

What APEC Leaders’ Week is and why Phu Quoc

APEC unites 21 economies of the Asia-Pacific region. Every year one of the members hosts the main leaders’ meeting. In 2027 the host is Vietnam, and the venue is unusual: not Hanoi or Ho Chi Minh City but the island of Phu Quoc. According to Vietnam’s Foreign Ministry, as cited by the press, the handover of the host role is planned for 19 November 2026 in Shenzhen at the 33rd APEC leaders’ meeting. Phu Quoc is part of An Giang province, and its authorities are responsible for the preparations. Leaders of 21 economies, business representatives and international journalists are expected. Exact dates are not given in verified sources: all that is known is that it is November 2027.

The main site: the APEC convention centre

The centrepiece is called the APEC Conference and Exhibition Centre. According to the Vietnamese English-language outlet Viet Nam News, its area exceeds 157,000 square metres, and the complex includes a ballroom of more than 11,000 square metres, a multifunctional performance hall and an international press centre; the investment is estimated at 21.9 trillion dong (about 860 million US dollars). Another source, the Saigon Times, gives a capacity of 6,500 seats plus an adjoining theatre of 4,000 seats. VnExpress in December 2025 described a column-free ballroom with an 81-metre span and an area of about 11,000 square metres, as well as a 2,000-seat venue for evening shows.

On readiness: in June 2026, according to the Saigon Times, the site was 46.58% complete and on schedule to finish by the end of May 2027. By 21 October 2026, according to VietnamPlus, about 98% of the reinforced concrete structure and 93% of the steel structure were built, and interior finishing was planned for the end of March 2027. The figures differ in which structures they cover, but the direction is clear: construction is moving fast.

Phu Quoc airport: what is being built

For a tourist this is the most important part. According to Viet Nam News, the airport expansion is estimated at about 22 trillion dong (about 870 million US dollars) and covers about 1,050 hectares. It includes a new T2 passenger terminal, a VIP terminal, a second runway 3,300 metres long, taxiways and an apron. The first phase is planned to start operating in April 2027, and a photo caption citing Sun Group says the same. In June 2026 the Saigon Times reported that some facilities were planned to open before 30 December 2026, so timelines differ between publications. On readiness: according to the Saigon Times in June, the runway was more than 96% complete, terminal T2 more than 45% and the VIP terminal 74.8%. According to VietnamPlus on 21 October, the VIP terminal’s structure was 100% done, T2 about 95% for concrete and steel roof, and the second runway 85%.

In December 2025 VnExpress wrote about a planned capacity of 20 million passengers a year and 120 aircraft stands with Changi Airport Group advising. According to later data from Viet Nam News, after an adjustment about 42 stands are planned by 2030 in front of T2 and the existing apron, plus about 45 stands on a separate apron, and about 51 hectares south of the airport are set aside for hotels, commerce and offices. If you are planning a trip in 2027, bear in mind that final dates for the terminal’s launch and any moving of flights may change, so check the schedule before booking.

Roads and rails

The island road and the new boulevard DT.975 should noticeably cut travel time. According to Viet Nam News, the route is about 20 kilometres long with a preliminary cost of 2.5 trillion dong. VnExpress gives a length of 19.26 km, a width of 62 metres, at least six lanes and a further 15 metres reserved for an electric tramway. VietnamPlus in October 2026 writes of 10 lanes and light rail in the central reservation. According to the Saigon Times in June 2026, the road was 69.5% complete and is due by the end of 2026. The APEC Boulevard, about 3 kilometres long and 68 metres wide, was 34.8% done.

Another project is an urban railway. The first line will link the airport and the conference zone; according to different outlets its length is 18 or more than 20 kilometres and the cost between 341 and 355 million dollars. In June 2026, according to the Saigon Times, the first phase was 16.5% complete, and a completion date is not given in the sources. So do not count on the metro on the very first day after APEC: check the state of the line closer to your trip.

Hotels and accommodation

According to Viet Nam News there are now about 500 accommodation establishments on the island, including more than 20 five-star hotels with nearly 11,000 rooms. The authorities believe more capacity is needed: in the Bai Dat Do area of 88.4 hectares 15 high-rise seafront hotels with nearly 6,500 rooms and 13 premium brands from five groups are planned. In the Nui Ong Quan area about 5,200 serviced apartments are earmarked. The final number of rooms by the time of APEC is not given in verified sources. For you this means: for November 2027, book accommodation early and with free cancellation, and base your expectations on actual occupancy.

What else is being built: water, power, a hospital

A summit needs more than a handsome hall. According to Viet Nam News and VietnamPlus, the programme includes two reservoirs, Cua Can and Duong Dong 2, of 7.5 million cubic metres each, new substations and a 220 kV substation costing about 2,165 billion dong, which is to be commissioned before March 2027. VietnamPlus also mentions a hospital, Mat Troi Phu Quoc. For island life these matter: the steadier the water and electricity, the fewer unpleasant surprises for tourists, especially in high season. The Saigon Times adds that symbolic structures are planned for each of the 21 member economies: details have not been disclosed yet.

Key deadlines on one scale

  • End of 2026: the DT.975 road and the APEC Boulevard are due for handover; one publication says some facilities will open before 30 December 2026.
  • End of March 2027: interior finishing of the convention centre and commissioning of the 220 kV substation.
  • April 2027: launch of the airport’s first phase according to Viet Nam News.
  • 31 May 2027: the final deadline for all 21 key projects (10 public and 11 with private participation, under government decision no. 948).
  • November 2027: APEC Leaders’ Week.

This scale is handy for planning: if you want to see the island before the big events, one logical option is the period after May 2027, when the main facilities should already be handed over, but before the November leaders’ week.

What it means for a tourist: go or wait

The press materials contain no reports of beach closures, flight restrictions or price rises for tourists. Viet Nam News, on the contrary, writes that normal traffic for residents and tourists will continue during the summit, and the railway is meant to ease the load on the roads. But it must be understood: events on this scale are usually accompanied by security measures and higher demand for accommodation and tickets. We found no official statements on the subject, so we promise nothing.

The practical conclusion: if your dates fall in November 2027, book flights and accommodation earlier than usual, leave a time buffer and follow the news. If your dates are flexible, the most predictable option is to go in winter or spring 2027, before the November summit. More about a winter trip to the island in our article on Phu Quoc in the 2026-2027 season, and a general overview of Vietnam for 2027 in the article about Vietnam in 2027.

Questions and answers

When exactly is APEC 2027? In November 2027; exact dates have not been named.

Where does it take place? On the island of Phu Quoc, An Giang province, in the new APEC Conference and Exhibition Centre.

Will the new airport be working? Launch of the first phase is stated for April 2027, but one publication also mentioned earlier dates; check current reports.

Will the island be closed to tourists? Verified sources contain no such information.

How many rooms will there be in 2027? There is no exact figure; at present the island has more than 20 five-star hotels and about 500 accommodation establishments.

What we do not know today

As of 24 November 2026 the following have not been published: exact dates of the Leaders’ Week, the final number of rooms by November 2027, restrictions on entry, flights and the operation of beaches during the summit, and the launch date of the urban railway. Figures differ between publications, and we have tried to show ranges. The article will be updated.

Sources

Information is current as of 24 November 2026. Construction timelines and travel conditions may change; check official announcements.